Project: Fauji Fertilizer Plant, Sadiqabad
Description:
LIFTING OF UREA STRIPPER
The rigging plan & job execution of inversion of striper at Fauji Fertilizer Plant near Sadiqabad (Pakistan), was carried out by HMA in April, 2000 during annual turnaround.
To lift the stripper specified as length 12m, dia 2.6m & weight 80 tons, crane coles colossus 250ton was deployed as main lift crane & manitowoc 4100w vicon used as tailing crane.
The whole activity took four hours to complete the inversion of stripper with the sequence of lifting the urea stripper to the ground, tilting and re-lifting the stripper to its foundations at 45m elevation